Project DPro (PMD Pro) Foundation

Practice / Sample Exam – English

124 votes, 4.5 avg
7143

Welcome to the Project DPro (PMD Pro) Foundation Practice / Sample Test.

This test allows you to practice a few questions of a DPro the certification exam. It helps to get into contact with the real exam questions (similar - not same questions). At the end of the practice test, you will be able to check your results and the correct answers.

You will also be invited to take a full practice / sample exam at a platform that has the same design, environment, and features. The full practice is important as it also tests your device for compatibility with the real exam platform.

Important notes:

  • Questions on this sample exam ARE NOT the same of the actual exam. These questions provide an overall idea of type of questions that you will find in the actual exam.
  • This is a practice exam - it is not valid as a DPro certification and it does not grant you any certificate or other document.
  • We recommend that you also take the Sample Exam at the PM4NGOs Sample Exams Platform.

1 / 10

Which are purposes of a Venn diagram?
1.   Analyzing the relationships between stakeholders
2.   Establishing roles and responsibilities of project stakeholders
3.   Mapping the influence of project stakeholders
4.   Identifying the stakeholders associated with a project

2 / 10

What are roles in the composition of a project board?
1.   A Senior User Perspective
2.   An Executive Perspective
3.   A Senior Supplier Perspective
4.   A Project Manager Perspective

3 / 10

What is the main purpose of ensuring the project implementation plan is 'iterative'?

4 / 10

What is the purpose of a concept paper?

5 / 10

What step in the Project Identification and Definition Phase includes deciding which elements will (and will not) be included in the scope of the project’s intervention?

6 / 10

Which of the following is an example of an internal control system?
1.  A record-keeping protocol for information management
2.  A vehicle mileage log
3.  A Segregation of Duties policy for financial roles
4.  A Monitoring and Evaluation Plan

7 / 10

Select the missing words in the following sentence:
Assuming a four level logical framework based on the Project DPro model, monitoring primarily corresponds to the activity and [ ? ] levels.

8 / 10

What is the correct sequence of project scheduling activities?
1.   Activity duration estimating
2.   Activity resource estimating
3.   Activity sequencing
4.   Activity definition

9 / 10

What are responsibilities of the Project Sponsor?
1.   Ensure organizational commitment and accountability for the project
2.   Take personal responsibility for succesful planning and implementation
3.   Ensure the overall success of the project
4.   Ensure that the organization “owns the process and results of the project.

10 / 10

What tool helps identify how a project will withdraw resources while ensuring that progress towards goals?

Before accessing the results of your quiz, please consider subscribing to receive news, invitation for webinars, and keep updated about PM4NGOs new guides, tools, and templates. Click the button below to see your results.

Your score is

The average score is 68%

Share this practice / sample test on your social media.

LinkedIn Facebook Twitter
0%

Did you like this format for practicing the exam? Please send any suggestions to improve it.

Thank you. Your feedback is valuable to help us improving the PM4NGOs website.